The Corocoro Oil Field is located in the Gulf of Paria in Eastern Venezuela approximately 32 kilometres offshore. The field has being developed using FPSO technology.
The FSO vessel was required to be spread moored in position, adjacent to the production facility by 10 anchor legs radiating from the bow and stern. Each mooring line consisted of a large 36 tonne steel sea bed anchor connected to a 4.75inch diameter heavy wire line, which is in turn was connected to a 5inch studless chain using heavy shackles and link plates. Depth of water at the FSO site was approximately 28 metres.
The installation procedure for the anchors was to pull pairs of anchors toward one another causing them to plough into the sea bed. This operation was designed to induce a nominal anchorage load of 700 tonnes into each line to ensure the anchors were firmly embedded in the sea bed.
Venezuelan contractor, Conar Construcciones, supported by ODL Services Inc were appointed as installation contractors for the spread mooring system. DLT were appointed to design and supply of the tensioning system, together with commissioning and operation of the equipment.
Stage 1.
Stage 2.
Stage 3.
There were 6 cross tensioning operations in total, with paired moorings selected to avoid cross over either during or after tensioning.
The tensioning operations were undertaken in 2007.