In 2016 DLT were awarded the contract by Mace Limited of United Kingdom to supply 2 No Pinned Climbing Jack Systems and Engineering support for the construction of twin 30 storey residential towers at East Village, Stratford, London. The project involved the construction of two high rise residential towers using pre-cast concrete construction.
The 'rising factory' concept was used to create a waterproof factory environment for the construction of each floor. The scheme used a temporary steel framed factory building erected over the top of each residential tower during construction. Each factory included two 15 tonne capacity overhead gantry cranes for materials handling and various levels of platforms for welfare facilities and materials storage. The factories were used for the construction of the structural columns and floor at the top and installation and sealing of the external cladding below.
Construction of each tower progressed generally at a rate of one floor per week. After each floor had been constructed the temporary steel ‘rising factory’ was lifted about 3.3m by the 4 x DL-CP250 pinned climbing jacks which remained static but lifted the climbing bar connected to the rising factory, allowing the next floor to be built. The total weight of each rising factory during lifting was approximately 900 tonnes.
Towers after final jump.
Rising factory being dismantled.
Rising Factory 2 ready for first lift.
During construction of towers, the weight of the Rising Factory was supported via 4 No. hydraulically operated Main Pins that connects it to the high rise building via 4No. temporary brackets, one fitted to each corner column of the building. All vertical and horizontal loads from the Rising Factory were transferred to the building via these Main Pins. During factory operation the Pinned Climbing Jacks and Climbing Bars were not subjected to any imposed loads.
During the jacking of the Factory the Main Pins were hydraulically withdrawn and the Pinned Climbing Jacks lifted the Climbing Bars which were fitted to the Rising Factory. The Pinned Climbing Jacks were each mounted on top of a temporary Bracket via a pair of link plates.
DL-CP250 Pinned Climbing Jack.
Hydraulically Operated Main Pin.
Arial view of first rising factory during assembly.